Evaluasi Pelaksanaan Perencanaan dan Pengendalian Jadwal Menggunakan Indikator Percent Plan Complete pada Proyek Gedung Olahraga di Cibubur

Authors

  • Mutia Floresa Wea Universitas Negeri Jakarta Author
  • Anisah Universitas Negeri Jakarta Author
  • Muhammad Iqbal Universitas Negeri Jakarta Author

DOI:

https://doi.org/10.63822/naaz0315

Keywords:

Percent Plan Complete, Time Control, Project Schedule Evaluation

Abstract

On-time completion is a key indicator of success in construction projects. However, in practice, many projects experience schedule deviations due to ineffective planning and unanticipated site constraints. This study aims to evaluate the implementation of planning and schedule control systems on the Sports Hall Project in Cibubur using the Percent Plan Complete (PPC) indicator as a time control tool, and to identify the factors that enabled the project to stay on schedule despite the PPC value not reaching the ideal target.This research uses a descriptive quantitative approach through the analysis of weekly PPC values, schedule deviations, and causes of delay (Reason for Non-Completion/RNC). The results show that the average PPC value only reached 19%, with significant fluctuations throughout the execution period. Although many activities experienced start and finish delays, the actual duration was shorter than planned, indicating acceleration strategies such as overtime and additional labor. The evaluation also revealed that the main constraints were delays in shop drawings, material procurement, and administrative issues.These findings indicate that despite the low PPC value, the project was still completed on time due to the project team’s adaptive responses carried out systematically and collaboratively. Therefore, PPC proves to be an effective evaluative tool for measuring the reliability of planning and the timeliness of project execution

References

Acebes, F., Poza, D., González-Varona, J. M., & López-Paredes, A. (2022). Stochastic Earned Duration Analysis for Project Schedule Management. Engineering, 9, 148–161. https://doi.org/10.1016/j.eng.2021.07.019

Aguome, N. M., Alaneme, G. U., Olaiya, B. C., & Lawan, M. M. (2024). Evaluation of lean construction practices for improving construction project delivery. Case study of Bushenyi District, Uganda. Cogent Engineering, 11(1). https://doi.org/10.1080/23311916.2024.2365902

AIA. (2023). Integrated Project Delivery: A Guide. https://www.aia.org/resource-center/integrated-project-delivery-guide

Alkas, M. J., Sari, D. P., Haryanto, B., & Ramadanri, N. A. (2023). Pengendalian Biaya dan Waktu Proyek dengan Metode Analisis Nilai Hasil Menggunakan Microsoft Project. Jurnal Rekayasa Tropis, Teknologi, Dan Inovasi (RETROTEKIN), 1(1), 8–15. https://doi.org/10.30872/retrotekin.v1i1.771

Ansah, R. H., Sorooshian, S., Mustafa, S. Bin, & Duvvuru, G. (2016). Lean construction tools. Proceedings of the International Conference on Industrial Engineering and Operations Management, 784–793.

Aslam, M., Gao, Z., & Smith, G. (2020). Development of Innovative Integrated Last Planner System (ILPS). International Journal of Civil Engineering, 18(6), 701–715. https://doi.org/10.1007/s40999-020-00504-9

Bajjou, M. S., Chafi, A., Ennadi, A., & El Hammoumi, M. (2017). The practical relationships between lean construction tools and sustainable development: A literature review. Journal of Engineering Science and Technology Review, 10(4), 170–177. https://doi.org/10.25103/jestr.104.20

Ditta, M. P., Studi, P., Sipil, T., Buana, U. M., & Project, M. (2025). Penerapan Teknologi Cloud-Based Scheduling dalam Monitoring dan Evaluasi Penjadwalan Proyek Konstruksi. 31(1). https://doi.org/10.36309/goi.v31i1.368

Emdanat, S., & Azambuja, M. (2016). Aligning near and long term planning for LPS implementations: A review of existing and new metrics. Lean Construction Journal, 2016, 90–101.

Fauchier, D., & Rankin, L. (2023). Advanced Work Packaging (AWP) and Lean Construction: A Comparison of Approaches Special Report 22-01c • Site Execution Planning & Control: Comparing Advanced Work Packaging (AWP) with Lean Construction and the Last Planner System ®.

Fauzan, R., Hidayat, B., & Suraji, A. (2023). DEVIASI KONTRAK DALAM PROYEK KONSTRUKSI : SEBUAH ANALISIS BERBASIS TEMUAN AUDIT KINERJA INSPEKTORAT DAERAH PROVINSI SUMATERA BARAT DOI : Pengadaan Barang / Jasa Pemerintah ( PBJ ) tugas dan fungsi pemerintahan , khususnya pemerintah dalam mencapai tujuann. 5, 324–333.

Ferdiandika, A. F., Nuciferani, F. T., & Choiriyah, S. (2024). Implementation Of The Last Planner System ( On The Construction Project Of Al-Falah Junior High School ). 05, 100–107.

Garcés, G., Forcael, E., Osorio, C., Castañeda, K., & Sánchez, O. (2025). Systematic review of Lean Construction: an approach to sustainability and efficiency in construction management. Journal of Infrastructure Preservation and Resilience, 6(1), 1–28. https://doi.org/10.1186/s43065-025-00119-1

Glenn Ballard, & Iris Tommelein. (2021). 2020 Current Process Benchmark for the Last Planner System ® of Project Planning and Control. In Lean Construction Journal (Vol. 155). www.leanconstructionjournal.org

Johari, G. J., & Amarulloh, S. (2022). Analisa Faktor Keberhasilan Proyek Kontruksi di Kabupaten Garut. Jurnal Konstruksi, 19(2), 362–372. https://doi.org/10.33364/konstruksi/v.19-2.895

Koilam, F. E., Dundu, A. K. T., & Arsjad, T. T. (2020). Perencanaan Waktu Penyelesaian Proyek Pembangunan Hotel Marron Resort Tomohon dengan Menggunakan Precedence Diagram Method. Jurnal Sipil Statik, 8(5), 749–754. https://ejournal.unsrat.ac.id/index.php/jss/article/view/35033

Lagos, C., & Alarcón, L. F. (2020). USING PERCENT PLAN COMPLETED FOR EARLY SUCCESS ASSESSMENT IN THE LAST PLANNER SYSTEM®. 469–480.

Lagos, C. I., & Alarcón, L. F. (2021). Composition and Impact of Reasons for Noncompletion in Construction Projects. IGLC 2021 - 29th Annual Conference of the International Group for Lean Construction - Lean Construction in Crisis Times: Responding to the Post-Pandemic AEC Industry Challenges, July, 817–826. https://doi.org/10.24928/2021/0210

LCI. (n.d.-a). Introduction to Last Planner System® (LPS®) for Design. Lean Construction Institute. Retrieved January 20, 2025, from https://leanconstruction.org/lean-topics/last-planner-system-for-design/

LCI. (n.d.-b). The Last Planner System® (LPS®). Retrieved March 17, 2024, from https://leanconstruction.org/lean-topics/last-planner-system/

LCI. (2017). Introduction to Last Planner System® (LPS®) for Design. Lean Construction Institute. https://leanconstruction.org/lean-topics/last-planner-system-for-design/

Lolomsait, M. P., & Setiawan, H. (2020). MANFAAT PENERAPAN LEAN CONSTRUCTION PADA PROYEK KONSTRUKSI : SYSTEMATIC REVIEW. 44, 24–26.

Mahamid, I. (2017). Analysis of schedule deviations in road construction projects and the effects of project physical characteristics: Journal of Financial Management of Property and Construction, 22(2), 192–210. https://doi.org/10.1108/JFMPC-07-2016-0031

Mandala, A., Widyaningsih, N., & Purwoko Kusumo Bintoro, B. (2020). Key factors of success in the application of last planner system in construction work. International Journal of Engineering & Technology, 9(3), 636–643. https://doi.org/10.14419/ijet.v9i3.30760

Mayo-Alvarez, L., Alvarez-Risco, A., Del-Aguila-Arcentales, S., Sekar, M. C., & Yáñez, J. A. (2022). A Systematic Review of Earned Value Management Methods for Monitoring and Control of Project Schedule Performance: An AHP Approach. Sustainability (Switzerland), 14(22). https://doi.org/10.3390/su142215259

Muniroh, M., Kempa, M., & Buyang, C. G. (2021). PENGENDALIAN BIAYA DAN WAKTU DENGAN EARNED VALUE CONCEPT PADA PROYEK PENATAAN BANGUNAN. Jurnal Simetrik, 11(2), 406.

Nursin, A., Fitria, & Sari, W. (2020). Last Planner System Pada Proyek Rumah Susun Transit Oriented Development. 2715–5668.

Nziza Global. (2024). The Importance of a Baseline Schedule in Project Management.

Pishdad-Bozorgi, P., & Beliveau, Y. J. (2016). Symbiotic Relationships between Integrated Project Delivery (IPD) and Trust. International Journal of Construction Education and Research, 12(3), 179–192. https://doi.org/10.1080/15578771.2015.1118170

PMI. (2017). A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE) SIXTH EDITION.

Power, W., & Taylor, D. (2019). Last planner® system and percent plan complete: An examination of trade contractor performance. Lean Construction Journal, 2019, 131–146.

Prasetya, E. B. (2018). Aplikasi Manajemen Proyek Konstruksi dengan Metode Critical Path dan Earned Value Management. RESISTOR (ElektRonika KEndali TelekomunikaSI Tenaga LiSTrik KOmputeR), 1(2), 53. https://doi.org/10.24853/resistor.1.2.53-68

Pribadi, R. A., & Abduh, M. (2022). Analisis Cost Performance Index (CPI) dan Schedule Performance Index (SPI) Menggunakan Metode Earned Value (Studi Kasus Pada Proyek Pembangunan Gedung Pasar Bucor Kulon Kabupaten Probolinggo). Jurnal Media Teknik Sipil, 20(1), 14–23. https://doi.org/10.22219/jmts.v20i1.14620

Pricillia, T., & Zulfachmi. (2021). Perbandingan Metode Pengembangan Perangkat Lunak (Waterfall, Prototype, RAD). Jurnal Bangkit Indonesia, 10(1), 6–12. https://doi.org/10.52771/bangkitindonesia.v10i1.153

Ronald Simanjuntak, M. A., & Huka, A. (2020). ANALISIS RISIKO PADA PROSES PERENCANAAN DAN PENJADWALAN PROYEK KONSTRUKSI INFRASTRUKTUR DI PROVINSI DKI JAKARTA. 397–403.

Rudd, J. (2022). Understanding Percent Plan Complete (PPC). https://blog.aphex.co/percent-plan-complete

Salam, I. Z., Setiono, S., & Rifai, M. (2023). Implementasi Last Planner System Pada Proyek Pgt. Matriks Teknik Sipil, 11(2), 152. https://doi.org/10.20961/mateksi.v11i2.75614

Sandy, N. R. A. (2017). Rancang Bangun Aplikasi Perhitungan Rincian Anggaran Biaya (Rab) Proyek Konstruksi Berbasis Web (Studi Kasus Cv Dipatih Jati …. http://repository.wicida.ac.id/770/

Scalisi, T. (2025). Maximize Efficiency with the Right Construction Management Methodology. Outbuild. https://www.outbuild.com/blog/project-management-methodologies-for-construction

Sekarningtyas, N., Priastiwi, Y. A., & Widayat, Widayat, 2024. (2024). Evaluasi Waktu Pekerjaan Bored Pile dengan Lean Construction Metode Last Planner System pada Proyek RSWS Makassar. Jpii, 2(3), 136–140. https://doi.org/10.14710/jpii.2024.22768

Sitohang, H., & Rohmah, A. (2020). Mitigasi Keterlambatan Jadwal Konstruksi Dengan Analisa Earned Value. Jurnal Teknik Sipil ISTN, X(1), 1–8. http://repository.istn.ac.id/id/eprint/1460

Siyoto, S., & Sodik, M. A. (2015). Dasar Metodologi Penelitian. Dasar Metodologi Penelitian, 83–84.

Suresh, D., & Annamalai, S. (2024). Effect of schedule management plan in project management worth using structural equation modelling. Anais Da Academia Brasileira de Ciencias, 96(2), 1–29. https://doi.org/10.1590/0001-3765202420230117

Swarjana, K. (2022). Populasi-Sampel, Teknik Sampling & Bias Dalam Penelitian (E. Risanto (ed.)). Penerbit ANDI. https://books.google.co.id/books?id=87J3EAAAQBAJ&lpg=PA1&ots=LOHAz5-Hyx&dq=populasi penelitian&lr&hl=id&pg=PR2#v=onepage&q=populasi penelitian&f=false

Telaumbanua, W. A. (2024). Analisis Penerapan Manajemen Waktu Pekerjaan Konstruksi Pada Proyek Pembangunan Gedung Dermina Beach & Cottage (Studi Kasus). 2504, 1–9.

Tembo, M., & Abdullahi, C. M. (2023). Improving the Efficiency and Effectiveness of Construction Project Planning and Scheduling Using Lean Principles. International Journal of Construction Engineering and Management, 2023(3), 75–80. https://doi.org/10.5923/j.ijcem.20231203.01

Zachawerus, J., & Soekiman, A. (2018). Faktor- Faktor Yang Mempengaruhi Kesuksesan Pelaksanaan Proyek Jalan Nasional Di Maluku Utara. Jurnal Infrastruktur, 4(01), 26–33.

Published

2025-08-13

How to Cite

Mutia Floresa Wea, Anisah, & Muhammad Iqbal. (2025). Evaluasi Pelaksanaan Perencanaan dan Pengendalian Jadwal Menggunakan Indikator Percent Plan Complete pada Proyek Gedung Olahraga di Cibubur. Jejak Digital: Jurnal Ilmiah Multidisiplin, 1(5), 3114-3125. https://doi.org/10.63822/naaz0315